Out of 1,739 central sector projects, 539 projects are

having ?me overrun and 209 projects are showing both

costs overrun and ?me overrun, as of February 1, 2021

This was informed in the Parliament

Of these 209 projects, 109 are in railways, 24 in roads,

transport and highways sector, and 21 each in power and

petroleum.

According to sta?s?cs minister Rao Inderjit Singh who told

Rajya Sabha, "The reasons for delay are project-specific,

depend on a variety of technical, financial and

administra?ve factors, and differ from project to project.”

However, delay in land acquisi?on and forest clearance has

been one of the important reasons for delay in the

comple?on of the projects as reported by the project

implemen?ng agencies. The delay in comple?on or ?me

overrun in respect of the original schedule of the Central

Sector Infrastructure Projects is one of the important

reasons for the escala?on of construc?on cost.

In a separate reply, he also said that technological

interven?ons like 'Computer Assisted Personal Interview'

(CAPI) has been introduced to reduce the ?me lag between

comple?on of field work of survey and publica?on of

results. Further, the ministry of sta?s?cs and program

implementa?on is developing a General Survey Solu?on

called 'e-Survey Instrument and Generalized Mul?modal

Applica?on' (e-SIGMA) and real ?me valida?on that would

reduce the ?me lag.